First step for second track

Cranbourne MP Pauline Richards visits Merinda Park Station.

Trains every ten minutes from Cranbourne are one step closer, with the first section of a second track installed as part of a $1 billion project to duplicate the line and remove the last four level crossings.

Minister for Transport Infrastructure Jacinta Allan announced the first of two new platforms at Merinda Park Station has opened, paving the way for services every ten minutes on the Cranbourne line.

Eight kilometres of track will be created to fully duplicate the line between Cranbourne and Dandenong, boosting capacity for 121,000 extra peak passengers each week once trains start running through the Metro Tunnel.

Supporting local jobs, the project is using ballast from Pakenham, more than 16,000 rail sleepers from Geelong and more than 22 kilometres of Australian steel rail welded in Sunshine. Around 500 metres worth of brand-new track was laid last week.

At Merinda Park Station in Lyndhurst, stage one of construction is now complete, with passengers now using the first of two new platforms, along with a new station entrance. An old platform was demolished in mid-March with work on the second new platform already underway.

Meanwhile, at Dandenong South, another major Cranbourne Line Upgrade milestone has been reached with every bridge beam now lifted into place for a new rail bridge that will remove the congested Greens Road level crossing.

More than 60 massive concrete bridge beams – weighing a combined 7000 tonnes and manufactured at a Melbourne factory – were installed in recent weeks. The crossing delays more than 23,000 vehicles each day in one of Melbourne’s busiest freight, logistics and manufacturing areas.

Making the most of rail crews working on the line, the Level Crossing Removal Project will also now deliver an additional package of track works through Dandenong.

These works, separate to the duplication, will untangle tracks around the junction between the Cranbourne and Pakenham lines, removing ‘speed limits’ for trains and making it easier for them to run to the timetable.

Working to open the second track by 2023, crews have already duplicated a mammoth amount of power and signalling including 250 overhead structures and hundreds of kilometres’ worth of cables.

The Cranbourne line will be the first to be level crossing-free.

The first part of the upgrade was completed in October last year when the Evans Road level crossing was removed – reconnecting the `communities of Lyndhurst, Lynbrook, and Cranbourne West.